2024-08-August-Controllability-Status-Update
Monthly Controllability Report
September 2024 Controllability Status Update
2024-09-September-Controllability-Status-Update
SONI Transmission Outage Summary 2024 (Week 44-45)
Summary of the SONI Transmission Outages over the next two weeks
SONI Transmission Outage Summary 2024 (Week 43-44)
Summary of the SONI Transmission Outages over the next two weeks
SONI Forward Work Plan 24-25
The SONI Forward Work Plan for 2024-25 outlines the various projects and work streams scheduled to be undertaken from October 2024 to September 2025. This appendix provides further details on the deliverables associated with Role 1 System Operation and Adequacy. It is important that this
appendix be reviewed in conjunction with the main Forward Work Plan document.
Appendix 2 Independent Expert
Appendix 2 Independent Expert
Quarterly Imperfections Cost Report Q4 Jul-Sep-TY2023-24
Quarterly update of factors affecting Imperfections costs.