Belfast Metropolitan Redevelopment Project Part 1 Preliminary Preferred Options Report

Report on the options for replacement of the Castlereagh - Carnmoney 110 kV double circuit, the multi-criteria analysis carried out and the preliminary preferred option carried forward for development

Mid Antrim Upgrade - Environmental Report

This document presents the work carried out by our environmental experts in relation to the options for the Mid Antrim Upgrade project. An environmental constraint modelling exercise was carried out to inform on the various constraints each option could encounter within the study area. SONI has used this information to inform our Preliminary Preferred Options report.