Updated SONI Connections Policy
Updated SONI Connections Policy following the decision on the consultation on options for conditions precedent for the acceptance of a connection offer by a new interconnector.
Interconnector Connection Policy Consultation – Response Report
Response Report regarding the responses received by SONI following the consultation on options for conditions precedent for the acceptance of a connection offer by a new interconnector.
Interconnector Connection Policy Consultation – Decision Paper
Decision Paper regarding the consultation on options for conditions precedent for the acceptance of a connection offer by a new interconnector.
Connections Register – 7th September 2021
SONI Connections Register as of 7th September 2021. (Published in compliance with PC6.4.1. of the SONI Grid Code)
Form of Standard Terms of a Connection Agreement
Form of Standard Terms of a Connection Agreement
Connections Register – 9th August 2021
The following document provides information on the current connections in Northern Ireland which are connected to the Transmission System, operated by SONI or have submitted an effective and valid application seeking a connection to the Transmission System. In addition the document also provides information on current connections in Northern Ireland which are connected to the Distribution System that has entered into a Generator TUoS Agreement with SONI or has applied to SONI for a generator TUoS Agreement.
Connections Register – 10th May 2021
The following document provides information on the current connections in Northern Ireland which are connected to the Transmission System, operated by SONI or have submitted an effective and valid application seeking a connection to the Transmission System. In addition the document also provides information on current connections in Northern Ireland which are connected to the Distribution System that has entered into a Generator TUoS Agreement with SONI or has applied to SONI for a generator TUoS Agreement.
Connections Register – 12 March 2021
The following document provides information on the current connections in Northern Ireland which are connected to the Transmission System, operated by SONI or have submitted an effective and valid application seeking a connection to the Transmission System.
Connections Register – 14th December 2020
The following document provides information on current connections in Northern Ireland which are connected to the Transmission System operated by SONI or have applied for future connection with us. In addition the document also provides information on current connections in Northern Ireland which are connected to the Distribution System, that have entered a TUoS Agreement with SONI or have applied to SONI for a TUoS Agreement. These include Transmission and relevant Distribution connection types as follows: Generation; Demand; AGU; DSU; and Storage.
Connections Register – 07 August 2020
This document provides information on current connections in Northern Ireland which are connected to the Transmission System operated by SONI or have applied for future connection with us.